What Happens After You Submit Your ADU Permit

What happens after you submit ADU permit drawings: plan check, comment letters, and resubmittal for a detached ADU, attached ADU, or garage conversion.

October 5, 2026 4 min read
Dark gray small house with a wooden porch surrounded by green trees
Between finished drawings and the first day of construction, there is the permit review.

In this article

Submitting the permit drawings for an ADU feels like the finish line of design. In practice, it is the start of a new phase. The city reviews the drawings, sends back comments, and the drawings are revised until everything is approved. Knowing what happens in this phase helps you plan your timeline, your budget, and your builder's start date.

Plan check is the phase after ADU design. Comment letters are normal, whether the project is a detached ADU, an attached ADU, or a garage conversion.

Step 1: Intake and completeness check

When the drawings are submitted, the city first checks that the application is complete. Many cities now accept submittals online. The completeness check confirms that the required forms, drawings, and documents are included, such as the site plan, floor plans, elevations, structural calculations, and energy compliance forms.

If something is missing, the application may be returned before review begins. This is one reason a complete, well-organized set saves time from the start.

Step 2: Plan check

Once accepted, the drawings go to plan check. Depending on the city and the project, several departments may review them:

  • Planning or zoning: setbacks, height, size, lot coverage, and parking rules.
  • Building: building code compliance, egress, fire separation, and accessibility where required.
  • Structural: the engineer's calculations and structural drawings.
  • Fire: access paths, sprinkler requirements in some cases, and wildfire zone requirements.
  • Public works and utilities: sewer, water, drainage, and work in the public right-of-way.

In California, once a permitting agency has a complete ADU application, state law generally requires it to approve or deny within 60 days when there is already a dwelling on the lot. The clock starts after the application is complete, not from the first incomplete upload; if you ask for a delay, that time usually does not count. If the ADU is submitted together with a new primary home, the city may hold the ADU decision until that primary application is decided. Other states have their own rules, and many cities publish target review times on their websites.

Two people marking corrections on a printed floor plan with pens
Plan check comments are normal. Each one is answered on the drawings and listed in a response letter.

Step 3: The comment letter

Very few ADU projects are approved on the first review. Most receive a comment letter, sometimes called a correction list. It lists the items each reviewer wants clarified, corrected, or added.

Common ADU comments include:

  • Missing or unclear dimensions to property lines and other structures
  • Fire separation details between the ADU and the main house or garage
  • Egress window sizes or locations in bedrooms
  • Utility details, such as sewer connection routes or electrical panel capacity
  • Energy compliance forms that do not match the drawings
  • Structural details that need more information
  • Notes the city requires on every set, such as specific code references

Comments are not a sign that the design failed. They are part of the process, and many are simple clarifications.

Step 4: Revisions and resubmittal

The design team revises the drawings and writes a response letter explaining how each comment was addressed, usually referencing the sheet where the change appears. Structural or energy comments go to the engineer or energy consultant. The revised set and the response letter are then resubmitted.

Many projects are approved after one round of corrections. Some need a second or third round, especially in cities with heavy workloads or projects with complex sites.

When you receive a comment letter, send it to your designer the same day. Every day it sits unanswered is a day added to your timeline.

Step 5: Approval and permit issuance

Once all reviewers approve, the city issues the permit, often after you pay any remaining fees. Some fees, such as school or utility fees, may be collected at this point. You will receive the approved, stamped drawings, which must be kept on the job site during construction.

Before construction begins, your builder will usually schedule the first inspection, often for the foundation. Inspections continue at key points through framing, utilities, insulation, and final.

Small bedroom with a bed beside a window in a wood-lined interior
After approval, the drawings become a real home. The review phase is what makes sure it is safe and buildable.

How to keep the review moving

  • Submit a complete set: incomplete applications are the most common cause of early delays.
  • Respond quickly: the city's clock usually pauses while it waits for your resubmittal.
  • Answer every comment: a response letter that skips items leads to another round.
  • Avoid design changes during review: new changes can trigger new comments.
  • Keep one point of contact: when the designer coordinates the engineer and energy consultant, responses stay consistent.

Ask who handles comments before you hire

Some design fees end at submittal, and responding to comments is billed separately. Others include comments until approval. It is worth asking before you sign. In my ADU projects, I coordinate responses and revisions until the permit is approved, and the project is considered complete when the city approves it.

If you are planning the budget for the whole permit phase, How Much Does It Cost to Design and Permit an ADU? walks through each soft cost. If you are already stuck in plan check on a remodel with drawings from someone else, my permit corrections service may help.

Modern house with vertical wooden siding and large windows
Clear, complete drawings are the fastest route from submittal to construction.

After submittal comes intake, plan check, a comment letter, revisions, and approval. Complete drawings, quick responses, and one coordinated team keep the process moving.

Want an ADU set that is ready for review?

My ADU packages include permit-ready architectural and MEP drawings, Title 24 compliance, and responses to city comments until approval. See your fee in minutes.

See your ADU design feeBook a free fit call
Arch Design by B logo
Beatriz Tercero Principal Building Designer
Arch Design by B, LLC
See Your Home Before It’s Built.