When homeowners budget for an ADU, they usually focus on construction. That is the largest cost, but it is not the first one. Before a builder can start, the project needs drawings, engineering, energy calculations, and a permit. These are often called soft costs, and they can surprise people who have only seen construction estimates.
ADU design and permit drawings are usually the first soft cost, whether you are planning a detached ADU, an attached suite, or a garage conversion.
This article walks through each soft cost, what it pays for, and what makes it higher or lower. If you are planning a full house rather than an ADU, I cover that in How Much Does It Cost to Hire Someone to Design a House?
The main soft costs of an ADU
Most ADU projects include some combination of the following:
- Design and permit drawings: the floor plan, elevations, site plan, sections, and details the city needs to review the project.
- MEP drawings: mechanical, electrical, and plumbing layouts, often required for a new dwelling unit.
- Structural engineering: calculations and structural drawings for foundations, framing, and lateral bracing.
- Energy compliance: in California, Title 24 calculations and forms. Other states have their own energy codes.
- Site information: property line information, and sometimes a survey or soils report.
- City fees: plan check, building permit, and in some cases school, impact, or utility fees.
Some designers include several of these in one fee. Others price only the drawings and leave engineering and energy work to separate consultants. When comparing quotes, make sure you are comparing the same scope.
Design and permit drawings
This is the core of the soft costs. The drawings show the city what you plan to build and show the builder how to build it. ADU design fees are usually based on size and scope, and these factors move them the most:
- Type of ADU: a garage conversion requires documenting the existing structure, while a detached ADU starts from scratch.
- Size and number of stories: a two-story ADU or an ADU above a garage needs more drawings and more coordination.
- Site complexity: slopes, easements, protected trees, and tight setbacks add design time.
- Level of design: a basic layout costs less than a fully designed unit with interior elevations, finish selections, and 3D views.
- Jurisdiction: some cities require more detail or more rounds of review than others.
For my ADU projects, the design fee is calculated from the square footage and scope, and you can see it right away in the ADU fee calculator. The permit-ready package includes architectural and MEP documentation and Title 24 energy compliance, with structural engineering included or excluded depending on your selection.
Structural engineering
Most new freestanding ADUs need structural engineering. The engineer designs the foundation, sizes beams and headers, and specifies how the building resists wind and earthquakes. Garage conversions and other work inside an existing structure may need less new engineering, or a different scope, unless walls are removed, the roof is changed, or the existing foundation needs repair. Your city and structural engineer decide what the set must include.
Structural fees go up with complexity: two stories, large openings, steep slopes, or difficult soils all add work. If you already have an engineer you trust, you can usually hire them directly and have your designer coordinate with them.
Energy compliance and Title 24
In California, newly constructed ADUs generally need to show Title 24 energy compliance. Conversions and alterations can follow different paths depending on the scope of work. Where full compliance documentation is required, that usually means calculations showing the insulation, windows, heating and cooling, water heating, and in many cases solar panels meet state requirements. The results go on forms that are part of the permit set.
Design choices affect this cost and the outcome. Large amounts of west-facing glass, for example, can make compliance harder. When energy compliance is part of the design process instead of an afterthought, it is easier to keep both the design and the budget on track.
Property lines, surveys, and soils reports
Your designer needs to know where the property lines are, where the existing structures sit, and where utilities run. A professional survey is not always required. Many cities have assessor maps and parcel records that, combined with your measurements and photos, are enough to start design.
A survey becomes more important when the ADU is close to a property line, when the lot has a significant slope, or when the city specifically requires one. A soils (geotechnical) report is sometimes required on hillside lots or where the city knows of expansive or unstable soils. Ask about both early, so they do not delay the permit later.
City and utility fees
City fees vary widely between jurisdictions. Common ones include plan check and building permit fees, which are often based on the project's valuation or square footage. Depending on the state and the size of the ADU, there may also be school fees, impact fees, and utility connection fees.
In California, state law limits some of these fees, but the categories are not identical. Many local impact fees do not apply to ADUs at or under 750 square feet of interior livable space, and larger ADUs are often charged in proportion to the primary home. School impact fees are treated separately and often do not apply below about 500 square feet; above that, a district may still charge. Utility connection fees and capacity charges are usually not the same as impact-fee exemptions, so they can still apply. Rules outside California are different. Confirm the current list with your city's permit counter, the utility providers, and, if relevant, the school district early in the process.
Plan check comments and revisions
Few ADUs are approved on the first submittal. The city reviews the drawings and sends back comments, often called corrections, and the drawings are revised and resubmitted. This can take one round or several, depending on the city and the completeness of the set.
Ask every designer you speak with whether their fee includes responding to city comments, and for how many rounds. In my ADU projects, I coordinate responses and revisions until the permit is approved, and the project is considered complete at approval, not when the final payment is made.
How to keep soft costs under control
- Choose a simple building form. Fewer corners and a straightforward roof mean less engineering and fewer details.
- Decide on the ADU type and size before design starts, so the drawings are not redone.
- Gather property information early: address, parcel number, photos, and any existing drawings of the main house.
- Pick one designer who coordinates engineering and energy work, so nothing falls between consultants.
- Make design decisions during design, not during plan check, when changes cost more.
ADU soft costs include drawings, engineering, energy compliance, site information, and city fees. Compare quotes by scope, and ask whether city comments are included.